The “How?” in getting the best New West Secondary School: A question of Project Delivery

Following my blog on the idea of designing the New Westminster Secondary School as a tower instead of the standard rambling low-rise form of school to deal with the site constraints, there has been a tremendous amount of response.

The resounding commentary has been not regarding “why?” but “how?” do we get this to happen.

This is a tremendously complex question. The design and fruition of community-based institutions is very heavily laden with a great deal of stakeholders, especially schools. Parents, community, neighbours, politicians, the Ministry of Education, the School Districts and the teachers all want, and should, have a say in such an important facility that will impact so many. Then there are the Architects and Engineers that also, normally, want to be a key and formative component to the project. Everyone has so much to gain and so much to lose.

After thinking about the “how?”, I keep coming back to one major component that will set the tone for such a project and will, ultimately, decide its success.

How will the project be delivered? What will be the method chosen to get the process going and the building built?

There are two main types of project delivery methods. One is the traditional Design-Bid-Build method and the other is Design-Build.

 

In the older and far more common process of Design-Bid-Build the project proceeds as follows:

  1. Stakeholders develop the Program, specifications and schedule for the project.
  2. A Request for Proposals is made to Architectural/Engineering teams to design the project.
  3. A team is selected based on their experience, people, schedule and fee.
  4. The design team meets often with the stakeholders to work out concepts then continue to solidifying the design up to the final construction documents. Everything is reviewed and commented on by everyone. Nowadays this is called the Integrated Design Process (IDP). (note: Robert Billard developed a version of the IDP called the Holistic Project Delivery (HPDtm) method to streamline it even further and make the process even more results driven. See the article on our site.)
  5. The Design is completed.
  6. The project is tendered for bids from qualified construction companies.
  7. The winning tender is selected by a panel comprised of stakeholders and based on experience, schedule and price.
  8. Construction starts.

 

By contrast, the following is the process set out in the Design-Build method:

  1. Stakeholders develop the Program, specifications and schedule.
  2. A Request for Proposal is made to qualified Architects/Engineers to act as the Owner’s Representative who will assist in refining the program and evaluating the Design-Build proposals.
  3. A Request for Qualifications is made to Contractors to assemble a team of Architects and Engineers.
  4. Three teams (typically) are selected based on their experience and robustness.
  5. The teams are given, typically, three months to develop a design proposal.
  6. While the competing teams are working on their designs, the Owner’s Representative develops a design with the stakeholders, meeting often hashing out concepts and testing the program and specifications. This final design will be used to evaluate the submissions by the competing proponents.
  7. During the three months, the teams meet a handful of times and present to a panel of stakeholders. Only the selected panel members are privy to these presentations and the results are not made public.
  8. Final designs are submitted for review. The submissions are tested against the Owner’s Representative’s prototype.
  9. The review panel, based on the advice of the Owner’s Representative, the price and the design that best meets the requirements of the project, selects a winner.
  10. An honorarium, typically in the order of $50,000 to $75,000 (dependant on the size of the project), is given to the losing proponents.
  11. The project begins construction.

 

Over the years I have worked on seven large and complex Design-Build projects. For one of these, I acted as the Owner’s Representative.

The decision to go with either project delivery method is difficult for large projects. There are many arguments made for the efficiencies and benefits of both. Over the past several years it has become more and more common for schools to use the Design-Build method.

 

The following are the perceived benefits and problems with each method:

 

Design-Bid-Build

Benefits

 

Negatives

 

Design-Build

Benefits

 

Negatives

 

Let’s examine the realities of the schedule for a typical school using these two methods:

 

Design-Bid-Build

Develop Program                                             6 months

RFP development                                           1 month

RFP and Team Selection                               2 months

Design                                                               10 months

Tender and Selection                                     2 months

Negotiations with Contractor                       1 month

Construction                                                   14 months

Total                                                             36 months (3 years)

 

Design-Build

Develop Program                                             6 months

RFP & Selection of Owner’s Rep.                 2 months

Refinement of Program & Design               4 months

RFQ & Selection of Proponents                   3 months

Competition                                                     3 months

Selection of winning team                            1 month

Negotiations with winner                               1 month

Construction                                                     14 months

Total                                                               34 months (2.8 years)

 

While, it may appear that the project is in the ground faster, a lot of time and money is spent early on. In terms of the argument that using Design-Build saves money, this is not the case. When a project, specifically a school, has been selected to go forward a budget is put in place. The project is intended to cost no more than this. If the use of the Design-Build process actually costs less than this budget, the money will be used for extras for the project. Having “extras” does not mean the school will be better because the winning bid is based on a bare-bones design with little innovation and cost-cutting in material and quality. Finally, the cost of the Owner’s Architect and the honoraria must be calculated into the overall project budget, typically hundreds of thousands of dollars.

In terms of making the right choice for the procurement of the New Westminster Secondary School, the answer to the “how?” is based on how much the community of stakeholders wants innovation, great Architecture, involvement and accountability by the design and construction teams. There is a reason why almost all notable Architecture in our cities such as art galleries, libraries, theatres, museums, office and condo towers are built using the traditional Design-Bid-Build method.

If we want to be assured of being proud of the resulting project, to feel a part of the process, embrace innovation, like designing a tower for the school, and further the great steps New Westminster has taken so far in fostering great Architecture, it appears the choice in